The project may reorganize existing rooms, extend the house or combine both. Under Austin HOME rules, the useful question may be whether the finished property is a two-unit or three-unit residential use rather than whether one home feels “accessory.” Confirm the official path before relying on a label.
Define the unit boundary
Draw where one dwelling ends and the other begins. Show exterior entrances, any internal connection, shared circulation, yards, storage, parking, meters and equipment. State which household controls each space.
The legal, fire, sound, privacy and system design depend on this boundary. A lockable door alone does not establish the complete solution.
Test the existing house as a host
Collect plans and inspect the areas affected by the work. Identify structure, foundation, roof, exterior walls, drainage, electrical service, plumbing and HVAC. For internal work, record ceiling height, windows, egress and the route to an independent entrance.
An addition also requires site feasibility. Map trees, setbacks, easements, impervious cover and construction access just as you would for a detached unit.
Choose between reorganization and addition
Reusing existing area can reduce exterior work but may take valuable rooms from the main household or create a compromised layout. Adding area can preserve the house plan but requires foundation, roof, drainage and exterior coordination.
Compare both options against household function, construction disruption, systems and complete cost. Do not assume fewer new square feet produces the better project.
Give each household independent daily function
Review sleeping, cooking, bathing, laundry, storage, waste, mail, deliveries and outdoor access. For multigenerational use, discuss privacy, supervision, accessibility and how the arrangement may change over time.
Place windows and doors to avoid unnecessary conflict. Consider where guests arrive and whether one household must cross the other’s private area.
Design sound control as an assembly
Noise travels through walls, floors, ceilings, doors, ducts and plumbing. Ask the design to state the separation assembly and flanking-path details. Coordinate equipment and wet rooms so ordinary daily use does not create avoidable disturbance.
“Insulated wall” is not a performance description. The drawings and construction scope should identify the materials and penetrations.
Coordinate structure and weather protection
For an addition, explain how new foundations, walls and roof connect to the existing building and how differential movement and water are handled. For internal work, identify bearing changes, openings and reinforcement.
Austin sun and heavy rain make the roof/wall transition important. Require flashing and drainage details rather than leaving the connection to field improvisation.
Decide what systems are shared
List electric panels, water, wastewater, heating/cooling, hot water, internet and controls. State whether each is shared or independent and how use can be isolated for maintenance. Confirm addressing and any provider requirements.
An independent household may still use branches from existing services, but capacity and route need evidence. See utilities and site work.
Plan construction around occupancy
Attached work can affect kitchens, bathrooms, hallways and services in the main home. The agreement should identify barriers, temporary closures, service shutdown notice, weather exposure, security and daily cleanup. Protect children, pets and residents from the work zone.
Ask which stages require the home to be vacant and whether that assumption appears in the schedule and owner budget.
Match the permit file to the actual work
The submission should describe the current and proposed dwellings, existing/new structure, life-safety separation, energy work and building systems. Austin requires unique addressing for new units and uses Residential Plan Review for new construction/additions.
Keep the approved set and conditions. If plan review changes the unit boundary or shared systems, update the priced scope before construction.
Price the effect on both sides
The budget should include not only the new unit but also demolition and reinstatement within the main house, temporary protection, service changes and finish matching. Identify owner-selected work that is merely convenient during the project and keep it separate from required ADU scope.
The Austin cost guide prevents main-house work from disappearing outside the headline.
Plan the occupied-home interface room by room
Mark every room affected by demolition, temporary walls, service shutdowns, dust control or trade access. Identify working hours, secure separation, bathroom and kitchen interruptions, pets, children and storage moves.
The contract should assign cleaning, protection and reinstatement. A short connection detail can disrupt a much larger part of the house, so the site plan and schedule should show the lived impact rather than only the new floor area.
Build a closeout test for two dwellings
Confirm addressing, locks, alarms, ventilation, utility labeling and approved separation on both sides. Retain final inspection records and the issued plan set. If the main house was altered, include those corrections and finishes in the same completion walk.
Frequently asked questions
Is an attached ADU the same as a duplex?
Not automatically. Austin’s classification depends on current code and the proposed arrangement. Ask Development Services and the design team to identify the correct use and application.
Must the units have separate utilities?
Requirements and owner preferences vary. Capacity, provider rules, metering goals and maintenance should be resolved for the address.
Can the connecting door remain?
That depends on the approved design and separation requirements. Treat it as a documented code/design decision.
Is internal conversion less disruptive than an addition?
It may involve less exterior construction but can cause more daily intrusion inside the occupied house. Compare the actual sequence and temporary conditions.